We were engaged by another contractor who we collaborate with regularly to assist in upgrading an 11kV and 3.3kV switchboard at a gas production plant.

We performed a number of tasks on this job. We handled the project management, schedule development and tracking, engaged with the customer and managed the execution. We also performed high voltage XLPE and paper lead cable terminations and jointing, created detailed designs for the high voltage switchgear control, ensuring the new system would integrate into the customer’s existing DCS/control system and looked after the commissioning of the plant upon completion of the shutdown.

We were contracted to replace a switchboard at a gold mine processing plant. The existing switchboard was installed in 1982 and had reached the end of its serviceable life. We were engaged to provide the detailed design and assist with the installation of a new 3.3 kV switchboard.